Principal
- FMA
- The Fabricator
- FABTECH
- Canadian Metalworking
Categories
- Additive Manufacturing
- Aluminum Welding
- Arc Welding
- Assembly and Joining
- Automation and Robotics
- Bending and Forming
- Consumables
- Cutting and Weld Prep
- Electric Vehicles
- En Español
- Finishing
- Hydroforming
- Laser Cutting
- Laser Welding
- Machining
- Manufacturing Software
- Materials Handling
- Metals/Materials
- Oxyfuel Cutting
- Plasma Cutting
- Power Tools
- Punching and Other Holemaking
- Roll Forming
- Safety
- Sawing
- Shearing
- Shop Management
- Testing and Measuring
- Tube and Pipe Fabrication
- Tube and Pipe Production
- Waterjet Cutting
Industry Directory
Webcasts
Podcasts
FAB 40
Advertise
Subscribe
Account Login
Search
Takt time brings objectivity to important lean manufacturing decisions
Why takt time is one of the most underutilized tactics in the lean manufacturing tool bag
- By Jeff Sipes
- March 13, 2020
- Article
- Shop Management
Imagine you land a large contract for a sheet metal subcomponent. You have capacity in laser cutting, bending, welding, finishing, and powder coating, but what about assembly? Your assembly department is already slammed with several large contracts. Can they handle another?
How do you make decisions about staffing, number of pieces of equipment, or number of shifts? Is it based on past experience, what the “wisest” person in the shop thinks, or what the supervisor believes? In other words, are these decisions made with no quantitative or scientific basis?
If so, you should consider a tool in the lean body of knowledge that can help you make informed and rigorous decisions. That tool is takt time. It’s one of the most underutilized and least understood of all the lean manufacturing ideas, yet it is possibly one of the most essential and powerful.
Defining Takt Time
Takt time, or time per unit of demand, is the pace you need to produce to meet customer demand. It equals available time divided by units of demand: Takt time = Available time/Units of demand. When the takt time (pace to meet customer demand) is compared to the cycle time (pace you are actually producing at), you have the information you need to assess whether or not you can meet customer demand.
You can see this in Figure 1. Operation A’s cycle time is greater than the takt time. That indicates a problem, because Operation A cannot produce enough to meet demand. Meanwhile, Operation B and C cycle times are both at or below the takt time. You should be OK to meet the demand, although you might consider some line balancing to optimize the cycle times and get them closer to the takt time.
Assuming the demand is fixed and you cannot move part of Operation A’s work to B and C, you must create more available time by, for example, adding another machine, person, or partial or extended shift.
Influencing Factors
Ingredients in the takt time calculation require decisions about operational matters often addressed in undisciplined ways. Input from company leadership is an absolute necessity. As you look at the factors that influence the takt time, you will take a more disciplined, scientific approach to managing the machine, workcell, and even the overall operation.
Assuming units of demand stay constant, some factors that influence the available time (the numerator in the takt time equation) are the following:
- People-paced operation. When you add people to a shift, you increase available time, which increases your takt time.
- Machine-paced operation. If you pick up 4 hours from another machine that is underutilized, then the available time increases and the takt time increases.
- Shift adjustments. Add a shift and available time increases.
- Overlapped work schedules. Change when the shifts start and end so that you gain additional clock hours during the workday.
Some factors that influence the units of demand (denominator in the takt time calculation) are:
- Variation in demand pattern. For example, demand might be higher on Monday and Tuesday before tapering off during the rest of the week.
- Seasonal demand differences. A classic example is a company that manufactures lawn care equipment. It might have heavy demand in late winter and spring followed by light demand in late summer and fall.
- Specific marketing or sales effort. This might cause the demand to spike during the promotion effort but might also influence a drop in demand.
- You don’t know what the demand will be. This might happen with a new product launch. There may be differing opinions on the potential demand. Further, customers might hesitate to commit to a level of demand because they essentially don’t know how successful the product will be.
Each scenario will affect the resulting takt time, and some of the decisions will require attention from leadership.
Optimal Staffing
Once you have the takt and cycle time information, you can use the optimal staffing calculation. This is useful in situations where there might be several operations in a cell or where you have multiple stations on an assembly line. The optimal staffing number gives you a target staffing level to work from. To calculate it, you take the sum of the cycle times and divide them by takt time.
Let’s continue the previous example and assume that the cycle times identified are valid. In this case, we find the optimal staffing by adding all the cycle times—90 seconds + 50 seconds + 60 seconds (as shown in Figure 1)—and dividing the sum by the takt time of 70 seconds: Optimal staffing = Sum of cycle times/Takt time. The result is 2.9, which gives us 3 people. This analysis can be useful when setting up a new cell or relocating an operation. The optimal staffing calculation helps make the decision objective rather than subjective.
An Example in Assembly
Say you have an eight-step line that has 8 assemblers, with one assembler at each step. You’re moving the line into a new building and have decided to study the operation and make modifications before relocating. To that end, you observe the operation and identify several obvious examples of waste. Using lean tools, you shorten the cycle time on several operations by driving out the muda.
The demand for this product is consistently 20 units per day. To meet that demand, you run one shift that, accounting for breaks and lunch, gives you 440 minutes of available time. So now, we divide 440 (available time) by 20 (units of demand) and get a takt time of 22 minutes (see Figure 2).
As you can see, the takt time (the red line at 22 minutes) is greater than each of the cycle times. Therefore, you can meet your customer demand. That said, the operations are not balanced. The minimum gap between cycle time and takt time is 2 minutes at Operation 3 and the maximum gap is 10 minutes at Operation 7. The other cycle times are spread between these two extremes.
Now you are faced with the question about staffing. Do you move the line “as is” with 8 assemblers or do you try to optimize by using fewer fully loaded workstations? If you run with fewer, then what is the number? Is it 4 people, 6 people, or maybe 7 people? This is where optimal staffing can help to set an objective target.
Again, the inputs to optimal staffing are the sum of the cycle times (18 + 15 + 20 + 13 + 14 + 18 + 12 + 17 = 127 minutes). The takt time is 22 minutes. To find optimal staffing, divide the sum of the cycle times (127 minutes) by the takt time (22 minutes). This gives you 5.8, which you round up to six people.
With 6 people as your optimal staffing target, you look for ways to combine tasks, move tasks around, create shared work, and develop other methods to move toward staffing with 6 or 7 people. Without the takt time/cycle time and optimal staffing analysis, you may well have simply said (or listened to your production supervisor say) we must stay at 8 people!
Don’t Overlook Takt
Takt time is one of the least understood yet most powerful tools in the lean toolbox. It brings objectivity to very important decisions about staffing, work loads, equipment investments, and the ability to meet your customer demand. The charts put the data into a visual format that helps explain it to the people affected by the analysis—especially the operators and assemblers directly involved.
As you continue on your lean journey, you may find that takt time becomes one of your “go-to” tools. Make those important decisions with confidence.
About the Author
Jeff Sipes
9250 Eagle Meadow Dr.
Indianapolis, IN 46234
(317) 439-7960
subscribe now
The Fabricator is North America's leading magazine for the metal forming and fabricating industry. The magazine delivers the news, technical articles, and case histories that enable fabricators to do their jobs more efficiently. The Fabricator has served the industry since 1970.
start your free subscription- Stay connected from anywhere
Easily access valuable industry resources now with full access to the digital edition of The Fabricator.
Easily access valuable industry resources now with full access to the digital edition of The Welder.
Easily access valuable industry resources now with full access to the digital edition of The Tube and Pipe Journal.
Easily access valuable industry resources now with full access to the digital edition of The Fabricator en Español.
- Podcasting
- Podcast:
- The Fabricator Podcast
- Published:
- 04/16/2024
- Running Time:
- 63:29
In this episode of The Fabricator Podcast, Caleb Chamberlain, co-founder and CEO of OSH Cut, discusses his company’s...
- Industry Events
16th Annual Safety Conference
- April 30 - May 1, 2024
- Elgin,
Pipe and Tube Conference
- May 21 - 22, 2024
- Omaha, NE
World-Class Roll Forming Workshop
- June 5 - 6, 2024
- Louisville, KY
Advanced Laser Application Workshop
- June 25 - 27, 2024
- Novi, MI